Estimate example · Commercial roofing

Commercial Flat Roof Estimate Example

A 7-page commercial roofing estimate: infrared survey, core cut log, tear-off and TPO priced by the square, unit prices for hidden damage and alternates.

Free plan available. No credit card required. See more document examples

At a glance

This estimate in numbers

About this example

This example is the estimate a commercial roofer in Indianapolis gives the manager of a 24,000 square foot warehouse whose 1998 built-up roof leaks at the drains. It tears off to the steel deck, replaces corroded deck at two drains, installs two layers of polyiso with tapered crickets, a gypsum cover board and a mechanically attached 60-mil TPO membrane, with new parapet flashing, coping, drains and scuppers and a 20-year manufacturer's warranty.

A flat roof estimate is only as good as the survey behind it, so this one leads with the evidence: an infrared scan, a core cut log showing which areas are wet and why a re-cover is not allowed, and the deck area to replace. A summary gives the total, the system and four weeks with the building open, then the assumptions and the scope. Costs run through four sections priced by the square, the linear foot and each, with a 3% contingency, and a table of unit prices sets in advance what any extra deck or insulation will cost. Three alternates, a sectioned schedule, warranty terms and acceptance complete it.

Who it is for

Commercial roofing contractors who estimate re-roofs for warehouses, retail buildings and offices after a roof survey.

Inside and how to use it

What this example contains, and how to make it yours

What's inside

  • A roof survey with infrared results and a core cut log
  • A summary with total, roof system, duration and assumptions
  • Costs by the square, linear foot and item in four sections
  • A 3% contingency and unit prices for hidden damage
  • Three priced alternates
  • A sectioned schedule, warranty terms and acceptance

How to adapt it

  • Lead with your survey: cores, moisture and deck condition
  • Price field areas by the square and edges by the foot
  • Set unit prices for hidden damage before work starts
  • Explain why you tear off instead of re-covering