Estimate example · Commercial HVAC

Rooftop Unit Replacement Estimate Example

A 7-page HVAC estimate for replacing two rooftop units on a school gym: existing conditions, roof plan, crane day, crew-hours, options and alternates.

Free plan available. No credit card required. See more document examples

At a glance

This estimate in numbers

About this example

This example is the estimate a mechanical contractor in Kansas City gives a charter school for replacing the two 22-year-old, 15-ton rooftop units over its gym and the gym exhaust fan. It covers the new high-efficiency units on curb adapters, a Saturday crane lift with its street permit, removal and refrigerant recovery, reconnection of gas, power, condensate and ducts, thermostats, startup, test and balance, and the city permit.

A facilities director has to justify replacement to a board, so the estimate starts with the condition of each unit on the roof and a roof plan showing where the crane sets them. A summary gives the total, the 30 tons of cooling and the single day the gym is closed, then the assumptions about curbs, permits and power. Costs run through three sections with equipment at distributor cost plus markup, installation in crew-hours and a 5% contingency for what the old units hide. The board's questions are answered on the page, three equipment options are priced side by side, and alternates, the lead-time schedule and terms close it.

Who it is for

Commercial HVAC and mechanical contractors who estimate rooftop unit replacements for schools, retail buildings and offices.

Inside and how to use it

What this example contains, and how to make it yours

What's inside

  • The condition of each unit and a roof plan
  • A summary with total, tonnage, downtime and assumptions
  • Equipment at cost plus markup, labor in crew-hours
  • The crane day and a contingency for the curbs
  • Answers to the client's questions and three equipment options
  • Alternates, a lead-time schedule and terms

How to adapt it

  • Document the existing equipment before pricing its replacement
  • Price the crane day as one line with its permit
  • Show equipment options as alternative totals
  • Explain lead time so the client orders early